Thursday, May 22, 2008

Which document describes the business need, the quantifiable criteria that must be met by the project, the key deliverables, and the final product of a project?

  • A. Project charter

  • B. Signed contract

  • C. WBS

  • D. Scope statement

Complex projects, involving multidisciplinary, multidepartment efforts, are most effectively managed by which of the following?

  • A. A strong matrix organization

  • B. A strong traditional manager

  • C. A functional organization

  • D. Multiple lead project managers

Of the following conflict management approaches, which is believed to lead to the least-sustaining positive results?

  • A. Avoidance

  • B. Problem solving

  • C. Compromise

  • D. Forcing

SMART objectives are ____________________.

  • A. objectives that are easily achievable

  • B. objectives used with the MBO management approach

  • C. objectives aligned with the organization's strategic goals

  • D. objectives that are specific, measurable, assignable, realistic, and time based